Problem/Objective

The objective of this Navy Metalworking Center (NMC) project was to use advanced metalworking technologies to reduce the weight and cost of airframe components on the Navy-Unmanned Combat Air System (N-UCAS). The ultimate goal was to demonstrate the viability of selected technologies on a full-scale test article. The project was coordinated with the Composites Manufacturing Technology Center (CMTC) project in a System Design and Manufacturing Demonstration (SDMD) program.

Accomplishments/Payoff

Process Improvement:
Two advanced metalworking technologies--advanced High Speed Machining (HSM) and Electron Beam Free Form Fabrication (EBFFF), a direct metal deposition process--and several advanced assembly techniques were selected for further development and demonstration during a previous concept exploration project. Advanced HSM was selected to manufacture ultra-thin aluminum spars and ribs. EBFFF was selected to produce lower-cost titanium components. The follow-on SDMD project was conducted in two phases; Phase I focused on design and development while Phase II focused on fabrication, assembly and testing.

Implementation and Technology Transfer:
The full-scale significant structural test article that was designed, built and tested under this NMC project met or exceeded all requirements established by NAVAIR. The next opportunity to transition these advanced metalworking technologies into the N-UCAS Production Vehicle will be the System Design and Development program in 2012. By inserting ManTech solutions early in the design process, this project will reduce life-cycle costs, preserve development schedules and promote timely transition to the N-UCAS Platform.

Expected Benefits:
The project demonstrated significant acquisition cost avoidance and a 16% to 35% weight reduction of affected parts. In addition to reduced fuel costs, the weight savings could lead to performance enhancements such as increased payload and endurance. The estimated cost benefits of using EBFFF, advanced HSM and advanced assembly techniques to produce a fleet of 150 N-UCAS aircraft are:

  • $25.0M manufacturing cost avoidance in titanium components
  • $3.8M manufacturing cost avoidance in aluminum spars and ribs
  • $12.1M assembly cost avoidance
  • $36.3M weight affected life-cycle cost avoidance

Participants

  • N-UCAS Program Office (PMA268)
  • Naval Air Systems Command (NAVAIR)
  • Navy Metalworking Center (NMC)
  • Boeing Phantom Works
  • Sciaky Inc.
  • National Institute for Aviation Research

About the Office of Naval Research

The Department of the Navy’s Office of Naval Research provides the science and technology necessary to maintain the Navy and Marine Corps’ technological advantage. Through its affiliates, ONR is a leader in science and technology with engagement in 50 states, 55 countries, 634 institutions of higher learning and nonprofit institutions, and more than 960 industry partners. ONR, through its commands, including headquarters, ONR Global and the Naval Research Laboratory in Washington, D.C., employs more than 3,800 people, comprising uniformed, civilian and contract personnel.