ARLINGTON, Va. (NNS) -- An innovative laser imaging technique, developed with funding from the Office of Naval Research (ONR), could cut more than 7,700 man hours from the manufacturing cycle of VIRGINIA-Class Submarines (VCS).

Successfully piloted in June 2008, the laser image projection technology allows General Dynamics Electric Boat´s (GDEB) Quonset Point, R.I., manufacturing facility to automate the layout of attachments during the early outfitting stages of VCS. This automation could result in an estimated 85 percent reduction in labor over the current method and could save up to $500,000 per hull.

The laser imaging technology uses 3-D digital ship design data generated by the OneStop Computer Aided Design (CAD) database. OneStop extracts positional data from the GDEB product model to determine the quantity and specific location of various attachments.

The GDEB project team cut its dependency on paper templates and string measurements using OneStop. In fact, the team located and attached 4,822 electrical and ventilation hangers and installed approximately 8,862 studs in 21 of the 22 VCS hull cylinders during the pilot program.

The laser image projection technology will ultimately equip production workers with direct access to the CAD model information needed to locate/mark points of attachment.

The GDEB project team continues to evaluate additional uses for the technology and in future efforts will include attachment points for piping and other fixed-point attachments. The cylindrical shape of the submarine´s hull is ideally suited to this technology, but other ship construction applications are also being considered and could result in cost savings for other Navy construction programs.

ONR´s Navy Manufacturing Technology (ManTech) Center for Naval Shipbuilding Technology (CNST) sponsored the pilot. CNST is a Navy ManTech Center of Excellence, chartered by ONR to identify, develop and deploy advanced manufacturing technologies in U.S. shipyards that will reduce the cost and time to build and repair Navy ships.

"ManTech sponsorship is making a huge impact here at Quonset Point," said Danielle Fernholz, point manager at GDEB´s Quonset Point facility. "We can´t thank [ONR] enough for the tremendous opportunities this program is affording us."

Previous ManTech efforts on the VCS are projected to help reduce design and engineering costs by $3.65 million per year and generate a per-hull savings of $5.275 million. Known as Design for Production (DfP), these efforts have yielded an optimized design and production environment for the VCS and are applicable across the shipbuilding and weapons systems industries.

For more details:

About the Office of Naval Research

The Department of the Navy’s Office of Naval Research provides the science and technology necessary to maintain the Navy and Marine Corps’ technological advantage. Through its affiliates, ONR is a leader in science and technology with engagement in 50 states, 55 countries, 634 institutions of higher learning and nonprofit institutions, and more than 960 industry partners. ONR, through its commands, including headquarters, ONR Global and the Naval Research Laboratory in Washington, D.C., employs more than 3,800 people, comprising uniformed, civilian and contract personnel.